Download Project structure to MSP with basic dates

Former Member
0 Kudos

Hi Experts

I am through with downloading project structure to MSP using open PS.

But the schedule is downloaded with forecast dates

I wish to download the basic dates (since i have rescheduled basic dates and hence baisc dates reflect the current status)

Is there any setting for determining which dates to be considered for downloaded structure?

Warm regards

ramSiva

Accepted Solutions (0)

Answers (1)

Answers (1)

Former Member
0 Kudos

What are you doing to get the forecast dates to come through rather than the actual dates?  To get the actual dates it is in the menu of the Open PS and it is a check box that allows you to import the actuals.