Finding The Planned Order

Former Member
0 Kudos

Hi,

Activities of the Network are contiaining Material. How to find out the materials corresponding to each Activity. And How to find Out the Corrseponding Planned Order for each Material.

Thanks & Regards,

Rahul

Accepted Solutions (0)

Answers (1)

Answers (1)

nitin_patoliya
Active Contributor
0 Kudos

Use below link for table linkage. From Proejct You should get WBS from WBS you should get Network activity via Counter that you need to pass to RESB table go get material assigned.

With Regards

Nitin P.

Former Member
0 Kudos

Hi Nitin ,

First of all thank you very much for your reply.

I am able to find out the material attached to the Activity and WBS Element linked to that activity.

But now i have to find out the Planned Order for the material in the stock segment of the WBS Element based on the WBS element linked to that activity.

How can i do this. Please help me.

Thanks and Regards,

Rahul

former_member203098
Active Contributor
0 Kudos

Hi,

You can get the planned order in RESB as told by

Nitin. Check the fields PLNUM, PSPEL, MATNR, AUFPS,

AUFNR.

Regards,