Dear Experts,
I want to know whether following is possible.
When creating a project initial schedule dates based on Activity Duration and Activity Relationships should reflect as Basic Dates. After project creation, when ever the Project Manager reschedule the project, those reschedule dates should be reflect as Forecasted dates.
By doing this the Project Manager will be able to identify Initial Plan as Basic Dates, Reschedule Plan as Forecasted Dates and Actual as Actual Dates.
Very Much Appreciate your Support,
Dileepa.
Select "Set of dates" as only Forecast Dates and then reschedule the project. (in Project planning board)
To be on a safer side, I suggest you to create a user status which will not allow you to change basic dates during scheduling.
Regards,
Amol Sarode
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Dear All,
I did reschedule Forecasting Dates using CN24 (Overall Network Scheduling) transaction. But after doing this, overall Project and WBS Elements dates does not changes based on the reschedule Network Time lines.
Further I have define "Network determines dates" as the Scheduling method in WBS Schedule Profile.
Very much appreciate your guidance,
Dileepa.