on 02-17-2010 6:36 PM
When you change configuration and move this to a QA client for testing and the testing fails...so you go back and make a different configuration change and move that one to the QA client and it passes just fine.....what would be the purpose of still moving the failed test (transport) to the production client?
Configuration Objects like Communication channels can be edited on any environment directly. You do not need transports for that. They are meant to be transported from the DEV system only because, the right Testing Business Systems are replaced while transporting. If the interfaces are not too comlicated, you might want to directly create them on QA too but not recommended.
VJ