Hello,

We are changing our business process and would like to have separate budgets per award year in GM. The scenario is as follows:

- One grant with multiple cost objects (each cost object represents a different award year)

- We need to budget, bill, and report in GM based on these budgets by cost object

- We need to budget by fiscal year in FM

Has anyone solved this problem for themselves, or can offer any suggestions?

Nancy

1 ACCEPTED SOLUTION

CesarCarreno
Advisor
Advisor
0 Kudos

Hi Nancy, it seems that your scenario can be solved using time-slices. You can check the Time sppliting rules under GM Budgeting custimizing. And the Grant master data - Tab Budget Validity Periods.

I hope this helps you.

Regards

César

View solution in original post

1 REPLY 1

CesarCarreno
Advisor
Advisor
0 Kudos

Hi Nancy, it seems that your scenario can be solved using time-slices. You can check the Time sppliting rules under GM Budgeting custimizing. And the Grant master data - Tab Budget Validity Periods.

I hope this helps you.

Regards

César