02-17-2010 5:22 PM
Hello,
We are changing our business process and would like to have separate budgets per award year in GM. The scenario is as follows:
- One grant with multiple cost objects (each cost object represents a different award year)
- We need to budget, bill, and report in GM based on these budgets by cost object
- We need to budget by fiscal year in FM
Has anyone solved this problem for themselves, or can offer any suggestions?
Nancy
02-18-2010 10:51 PM
Hi Nancy, it seems that your scenario can be solved using time-slices. You can check the Time sppliting rules under GM Budgeting custimizing. And the Grant master data - Tab Budget Validity Periods.
I hope this helps you.
Regards
César
02-18-2010 10:51 PM
Hi Nancy, it seems that your scenario can be solved using time-slices. You can check the Time sppliting rules under GM Budgeting custimizing. And the Grant master data - Tab Budget Validity Periods.
I hope this helps you.
Regards
César