on 02-17-2010 2:18 PM
Hi,
We are using assembly processing to create project from quotation. Once the project is saved, reservations are created for non stock materials (Item cat N). The status on the network and activity is CRTD. I have checked the value for field 'Res/Purc.Cre' for the material and IMG settings for the network is 2. I can see the reservations for that material against the network in MD04.
I have deleted the material from the activity and re added the same manually. when I checked for reservations, I could not find any against that network in MD04.
Can any one tell me why the reservations are created when project is created automatically
Regards,
Laxminarsimha
Dear, Please understand that Reservations are always created wheneve you assign components to network activity even in CRTD status i.e., irrespective of your value in 'Res/Purc.req'. The value which you maintain in 'Res/Purc.req' tells system when to activate the reservation not when to create the reservation. For example, if your 'Res/Pur.req' has value 2 i.e., From release, the reservations will be created in CRTD status, and it will be activated in REL status i.e., will be relevant for further planning like MRP run only on release of activity.
In your case even the reservations are created in CRTD status, you wont see the reservation in MD04. Please check in MD04 for the new project(for which the requirement class config are changed as per the note mentioned by Kabir), you wont find the reservations.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi Laxminarasimha,
Please refer Note: 53494.
Regards,
Kabir
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi Laxminarasimha,
As per the note, in Case #2 - A material participates in inventory management, is planned and to be maintained in the sales and distribution document as well as for example in a network or production order. When processing the assembly with network, the requirement is to be released on time from a network and not from the sales and distribution document.
So that means it should not affect the planning in PS. And for that we need to do a config for requirement class as mentioned in Note.
I would suggest you replicate the scenario in your Sandbox / DEV server and test the same.
Regards,
Kabir
Hi Kabir,
I have replicated the scenario in our Sandbox. As suggested in note, I have changed the config settings in the requirement class. 'Requirements--> No MRP --> 1
But still the reservations are generated for the non stock materials in CRTD status. I have created new material without MRP view and added to the project but the reservation is created for this material too. Is this a standard behavior or am I missing some thing
Regards,
Laxminarsimha
User | Count |
---|---|
95 | |
11 | |
11 | |
6 | |
6 | |
4 | |
4 | |
3 | |
3 | |
3 |