Hi all,

Can anyone let me know how to execute forecasting in the background using the job number?

Thanks

Pooja

Accepted Solutions (1)

Accepted Solutions (1)

Former Member
0 Kudos

Hello Pooja,

The below links gives you an idea about the activity and job creation.

http://rb3pp001.server.bosch.com/SAP-HELP/OnlineDoku_SCM70/PlainHTML/helpdata/EN/5f/176d4160168147e1...

Regards,

Siva.

Answers (1)

Answers (1)

somnath_manna
Active Contributor
0 Kudos

Running Statistical Forecast in background as a job requires setting up an activity where you select the forecast profile. Then in DP Background job assign the activity and specify the selection profile with suitable Aggregation Level.

You need to ensure that Planning Book / Data View selected in the background job should have appropriate Time Bucket Profile as per Periodicity maintained in the Forecast Profile (like Weekly or Monthly).

Hope this helps.