on 02-17-2010 1:32 AM
Hi experts,
I am trying to test ETO scenario with using iPPE as follows;
1. Create Structure node with valiant configuration with some materials.
2. Copy it to M-BOM (PP BOM - Super BOM?)
3. Crate SO with variant configuration, then copy SalesOrder(SO) BOM from M-BOM.
and also automaticaly Project with networks are created.
4. Process BOM transfer from SO BOM to Network.
5 ....
Is it possible solution.
And the customer don't want to copy BOM from iPPE and need to create SO BOM from iPPE. is it possible. if so, please give some operation or customizing settings.
thanks always.
best regards, Takashi
This thread was "answered".
Discussed with my collegue, Sales order can not read iPPE node anymore.
So we have only two options;
1. Transfer M-BOM into PP from iPPE node.
Then create SO.
or
2. Transfer E-BOM directly to PS.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
99 | |
11 | |
11 | |
6 | |
6 | |
4 | |
4 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.