on 02-16-2010 6:33 AM
Dear Experts,
We followed the process that:
1.We made a SO withoot WBS element
2.Run the MRP
3.It gives the PR Qty
Now we assign a WBS element in Sales Order and want to run MRP for the sales order and it gives error msg"Sales Order does not allow make to order production".Please suggest us that how should we proceed.
Thanks in advance
Warm regards:
Nishu
Check the Sales order type and ask the SD team to do the needful config
Rgds
Abraham
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Make some changes in the materials
MM02 --MRP views change the strategy group to Make to order production and MRP type PD deterministic MRP.
Now try running the MRP to create the Planned orders or PRs.
Then Convert the Planned order to Production orders from the SAP logistics screen.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.