on 02-15-2010 6:39 PM
Hi,
When BDLS job is in active state.Cant we have another one running.Its getting cancelled saying that a process is running.Thanks in advance.
Hi,
You can have only one BDLS session running at time.
Regards,
Sanujit
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Yes , this still will work if the tables the conversion is happening is not the same . You can BDLS in two sets say tables A-Z
and not (AtoZ) , if you are running BDLS simultaneously with the same logical systems without mentioning any tables BDLS will fail.
Edited by: Mann Mohandas on Feb 18, 2010 3:46 PM
User | Count |
---|---|
84 | |
10 | |
10 | |
9 | |
7 | |
6 | |
5 | |
5 | |
4 | |
4 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.