Dear All,

Since yestardayin production server the date format of invoice is like 12.02.2010,but form morning it is comming like 2010.02.12.

I have checked in quality and it is still comming like 12.02.2010.

Could you please tell me why is it comming?

Regards,

Amar

Accepted Solutions (1)

Accepted Solutions (1)

Abhijit74
Active Contributor
0 Kudos

Hi,

Go to System>User Profile>Own Data. Then go to default. Change the format of the date. I think somehow it has been changed by any other user.

If this is not the case please let me know.

Thanks,

Abhijit

Answers (1)

Answers (1)

Former Member
0 Kudos

Dear Amar,

1 Check the user profile for default type od date value in production system and compare it with quality. If this is not as per the quality system then change it.

2 if both system quality and production both have same date format then you have to debug and find out the issue.

Hope you need not to go for second point.