on 02-15-2010 7:33 AM
Hi Gurus,
I am trying to upload a project from MSP to R/3. Whenever, I am doing so, system gives an error message "CO501 - Project definition update". Actually, I am using a custom calendar but according to the error message the dates are not in the calendar ( though the dates are well within the calendar period). If I create a project directly in CJ20N with Calendar as 01 and if I upload then system uploads all the WBS elements with Starting from 01st Nov' 1999.
I had maintained the custom calendar in MSP settings as well. Where i am going wrong ? Why these dates are getting changed to Nov 99 whereas I had maintained in 2010. What else I need to do ? I am using OpenPS4MSP version 4.0.
thanks in advance.
Vinodh
Latest version used and resolved.Closed.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
95 | |
11 | |
11 | |
6 | |
6 | |
4 | |
3 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.