i am currently working on a Engineering construction industry project.Here the client needs to bill the customer depending upon the progress made in the project every month. The line items has to be billed depending upon the completion of work as per the rates agreed in the contract.
Now we have to get these percentage completion of work from Project system so that we can bill the customer.kindly give me insight to map this scenario.
The prompt response will be rewarded with suitable points.
Thanking you,
Best Reagrds
Please check the following link:
http://help.sap.com/saphelp_erp60_sp/helpdata/en/dd/5606b5545a11d1a7020000e829fd11/content.htm
Thanks.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi,
Use milestone billing for different % of work completion.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Dear,
If I am not wrong then you must be talking about Milestone Billing here are some linked related to the same,
http://www.saptechies.com/billing-plan-for-milestone-billing/ or
http://www.sap-img.com/sd006.htm
Regards
AJIT K SINGH
HAPPY TO HELP U
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
110 | |
12 | |
11 | |
6 | |
5 | |
4 | |
4 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.