Dear All,

i am currently working on a Engineering construction industry project.Here the client needs to bill the customer depending upon the progress made in the project every month. The line items has to be billed depending upon the completion of work as per the rates agreed in the contract.

Now we have to get these percentage completion of work from Project system so that we can bill the customer.kindly give me insight to map this scenario.

The prompt response will be rewarded with suitable points.

Thanking you,

Best Reagrds

Accepted Solutions (1)

Accepted Solutions (1)

Former Member
0 Kudos

Answers (2)

Answers (2)

Former Member
0 Kudos

Hi,

Use milestone billing for different % of work completion.

ajitsingh6
Active Contributor
0 Kudos

Dear,

If I am not wrong then you must be talking about Milestone Billing here are some linked related to the same,

http://www.saptechies.com/billing-plan-for-milestone-billing/ or

http://www.sap-img.com/sd006.htm

Regards

AJIT K SINGH