Project Scheduling in Planning Board

Former Member
0 Kudos

Dear Experts,

When I am scheduling the project (all wbse and network) through planning board, after clicking the schedule icon a pop-up window is coming and in the pop-up window it is written Select set of dates .

Any idea why this pop-up is coming.

How can I remove poping-up of Select Set of Dates Window.

Thanking you.

Best Regards,

Abdul.

Accepted Solutions (1)

Accepted Solutions (1)

virendra_pal
Active Contributor
0 Kudos

this is quite strange

from my understanding at least one set of dates is mandatory and this should not come when you click on scheduling icon

when you extrapolate dates then it is fine as the system may want ot know basic or actual dates

click on the set of dates view button on the planning board

make sure that basic dates and earliets dates is set (ticked)

then no pop up shouold come

Former Member
0 Kudos

Dear Mr. Virendra Pal,

Thank you very much for the detailed reply.

I have removed the tick for forcast date and actual date from set of dates view button on the planning board, and kept tick only for basic dates and earliets dates, Now the pop-up window is not coming, when I am clicking schedule icon.

Thanking you.

Best Regards,

Abdul.