question about scheduling agreement va32

Former Member
0 Kudos

hi sd experts,

i have two questions about SA in VA32, i use forecast delivery scheduling , not JIT delivery

1.

why the "Cml. iss. qty."(Cumulative issued quantity) can not cumulate the previous year's issued qty,

e.g.: in 2009, the issued qty is 200, in 2010, the issued qty is 300, and the current year is 2010,

but in field "Cml. iss. qty." , the qty is 300, not 500, why 200 is missing,

2,

when i use "New dlv sched w/proposal" function to create a new delivery scheduling,

there are some schedule lines which order qty is zero will be generated, why??

e.g:

the first delivery scheduling :

Dlv.schedule 1

Dlv.sched.date 2009.11.19

date date time order qty cml.released qty

D 2009.11.20 00:00 72 72

D 2009.11.27 00:00 144 216

D 2009.12.04 00:00 144 360

D 2009.12.11 00:00 144 504

D 2009.12.18 00:00 144 648

D 2009.12.25 00:00 144 792

when i create Dlv. scheduling 2

Dlv.schedule 2

Dlv.sched.date 2010.02.04

date date time order qty cml.released qty

D 2009.11.20 00:00 72 72

D 2009.11.27 00:00 144 216

D 2009.12.04 00:00 144 360

D 2009.12.11 00:00 144 504

D 2009.12.18 00:00 144 648

D 2009.12.25 00:00 144 792

D 2010.02.04 00:00 0 792

D 2010.02.04 00:00 0 792

D 2010.02.04 00:00 0 792

D 2010.02.04 00:00 0 792

D 2010.02.04 00:00 0 792

D 2010.02.04 00:00 0 792

D 2010.02.05 00:00 8 800

thanks in advance,

gj

Accepted Solutions (0)

Answers (1)

Answers (1)

Former Member
0 Kudos

On your first item you need to check the FY variant setting on your ship to. If no FY variant exists in the ship to and the s/a is not set up as a ZBB type s/a then a cumrollback will occur on 1 Jan which will set your cum GI qty to include only qty PGI'd in that calendar year