on 02-12-2010 9:17 AM
Hi Friends,
While running CJ44 for overhead calculation of project am getting the message
The objects that you selected do not have any actual costs
Message no. KA460
Diagnosis
There are no actual costs on the objects selected.
System Response
The system therefore does not calculate overhead for these objects.
Any inputs.
Regards
Amit
Amit
The message clearly says that, you have not incurred any actual cost on your WBS &/ activity.
CJ44 is for calculating the overhead costs on the actual costs, your project has incurred.
First you post actual cost on your project. Then run CJ44.
Prerequisites:
1. Assign costing sheet to your valuation variant
2. Assign Overhead key to your WBSE manually in your project or else you can maintain it in your project profile.
I hope this, helps you.
Amaresh Makal
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
108 | |
12 | |
11 | |
6 | |
5 | |
4 | |
3 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.