Hi Experts
I wish to have a predetermined layout for CNE5 report (only with progress values), but i donot find the feature for managing layout.
Is there any clue for this.
warm regards
ramSiva
this is available in the initial screen
when you run transaction CNE5 you will be asked to enter PS profile - enter that
then you will com to the screen where you will need to put the project number etc
Here in menu path
View -> choose fields
then save as variant etc