I have been looking at the option of using Component Scrap (In ECC MRP4 screen in Material Master).

Looking in APO I have not been able to find the same item.

I may be missing the point completely but am getting desperate now.

We plan ALL materials in APO and need to be able to increase the procurement proposlas on specific input materials.

Thanks in advance.

Accepted Solutions (0)

Answers (3)

Answers (3)

Former Member
0 Kudos

Hi,

Assembly or operation scrapwill be reflected in APO as activity scrap but component scrap will be added to component quantity while transfer of PPM. There is no feild in APo showing component scrap%.

Santosh

Former Member
0 Kudos

Hi UK User,

The scrap % will be populated to APO and can be displayed in

transaction /sapapo/scc03, under activities in the following

sequence

Activity, description, activity type, activity type description,

Scrap%

Please check and confirm

Regards

R. Senthil Mareeswaran.

Former Member
0 Kudos

Hi,

Though there is no specific feild called component scarp in APO product master. Quantity of components is increased by scrap% while transfer of PPM in APO.

So planning will plan based on this PPM correct quantities.

For more information follow the link http://help.sap.com/saphelp_scm50/helpdata/en/9b/954d3baf755b67e10000000a114084/frameset.htm chek in integration of routing section.

Hope this helps.

Regards,

Santosh