on 02-11-2010 9:08 AM
Hi
I have settled WBSE fully and now Asset number got created.
This Asset number I have linked with Equipment Master in PM Module.
My requirement is that how to get Life for this Equipment and also Equipment Replacement Value ?
So that I can come to know that whether to maintain this Equipment or Replace ?
Is any Process/TCD/Report available in Standard SAP PS/PM/AM/FI ?
Swapnil Kharul
Closed.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
in asset management FI-AA you should be depreciating this asset and also have the valuation for the asset - you can maintain different valuation methods etc - this is not in PS scope
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
99 | |
9 | |
9 | |
5 | |
4 | |
3 | |
3 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.