Hi all I am stumped. We have a new plant that we are using ATP and planning material with, and whenever you enter a part on a Sales Order for the last 5 to 7 days the month it propose it to the following month. The part is a FERT with 1 days processing time so I donu2019t see how that would play into the picture. I have gone over the materials a couple times any one got some ideas? Below is the setup of the materials.
So an example I place an order for the 23 of March and it confirms for that date, I place an order for the 25 and the order proposes the 1st of April.
Finished Part has plan Part as planning material Planning Material consumes Raw
Finished Part
MRP TYPE : P3
Planning Time Fence: 30
Lot Size: EX
In house Production: 1
Strategy Group: 63
Consumption Mode: 2
FWS Consump: 30
BKWD Consump: 15
Planning Part : PLAN
Avial Check: 02
Planning Part
MRP TYPE : PD
Planning Time Fence: 30
Lot Size: EX
Special Procurement: 50
In house Production: 1
Strategy Group: 63
Consumption Mode: 2
FWS Consump: 365
BKWD Consump: 15
Avial Check: 02
Raw Material
MRP TYPE : P3
Planning Time Fence: 30
Lot Size: EX
Plan Delivery: 84
Goods Receipt Procs: 1
Consumption Mode: 2
Avial Check: 02
Hi there, are you able to confirm dates between 25 and 31 even manually? Have you checked your shipping point related settings?
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
103 | |
12 | |
11 | |
6 | |
5 | |
4 | |
3 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.