Is there a method/best practice for transporting CJEx report changes between clients or is it recommended to make the necessary changes in each client?

I have a user that requested adding period as a parameter to one of the reports, she liked the results in DEV but the changes were not included when I created a transport of the report.

Thanks in advance.

Jon

Accepted Solutions (1)

Accepted Solutions (1)

virendra_pal
Active Contributor
0 Kudos

I have had similar issues in the past when transporting from CJex transactions and had to resort to do the changes direct in the system.

Make sure you tick all the boxes for report, form amd key figures

But , yes it is safest to do at cutover direct in QA/PRD, anyway reports are required a little later after go-live