on 02-10-2010 10:17 AM
Dear Friends,
I am creating inspection plans using BDC. The MIChas 2 versions. When i am using version 1, the inspection plan is created. Whereas when i am using MIC version 2 i am getting error "error occured while checking type group".Kindly let me know how do i resolve this.
Regards
Vivek
Thanks to everyone for replies. Issue resolved.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi,
In Ver 2 of MIC some control indicators are differ from Ver 1, pl check check if you are assigning correct sampling procedure for mic ver 2 in inspection plan .
Regards,
Neeraj Singh
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi neeraj,
You were right. Wrong sampling procedure was being assigned. But i have a problem. When i click on options to select sampling procedure, only one sampling procedure is coming. Is sampling procedure a plant level setting? when i am creating sampling procedure it does not ask for plant. From where does it select plant?
Vivek
Hi,
Thanks for the reply. when i am trying to create a inspection plan in other plant, we have 4-5 sampling procesures to select from. But for this perticular plant where we are having problem, its showing only one. How do i get more options?How do i extend a sampling procedure to a new plant.
Vivek
Edited by: vivek mankad on Feb 23, 2010 7:57 AM
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Check wherther MIC2 is Released.
Also check what is validity date of MIC2.
Most probaly these could be the reasons
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
103 | |
12 | |
11 | |
6 | |
5 | |
4 | |
3 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.