on 02-10-2010 6:00 AM
Dear Experts,
Is it possible to implement Refurbishment management process without having different valuation types for materials?
Reason is that in our company we have not activated split valuation for engineering materials. but there is a requirement to implement refurbishment order process,
How this can cater?
thanks in Advance....
Hi Sank,
I think you need split valuation for refurbishment .. first thing what you can do is to identify the materials for refurbishment and activate split valuation for that and ensure that there is no stock for those materials and then start up ur process ..
regards
pushpa
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.