Hello Friends,
I have an scenario of ECP and have already created the planning form and costing model, but when i go the project builder and click on project definition and then click on ECP icon it throws the below error. Even though i have clicked on planning elements of all the wbs elements in the projects. But i havent done any material component in the projects. Kindly guide me
Project or project branch does not contain any planning elements
Message no. KPN082
Diagnosis
The project or project branch to be processed does not contain any planning elements.
System Response
The system cannot create the costing.
Procedure
Select the WBS elements you want to cost as planning elements.
Note that costing is not possible for plan-integrated WBS elements, even though they are planning elements.
-
Thanks and Regards,
Praveen B M
is the integrated planning indicator ticked
if yes then remove and try
may have to create a new project
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
You must define at least one WBS as planning elemt. Put flag in field Operative indicators/Planning Element (PRPS-PLAKZ)
Regards, Anronio
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
101 | |
12 | |
11 | |
6 | |
6 | |
4 | |
3 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.