on 02-09-2010 9:40 AM
Hi,
I uses BAPI_NETWORK_MAINTAIN function to schedule a network but when start date is older than today the function automatic user today for the start date. How can I use the start date older than today? Please help me!
Thank!
Edited by: Cuong Nguyen Cao on Feb 9, 2010 10:47 AM
Check your settings in tx OPU6, this is a configuration at plant level, enter to one of them, you will se a field called "Start in the past" press F1 on that one and there you will find your answer.
Also there is a checkbox for automatic scheduling, that might help you depending on your scenario.
Best Regards
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
This message was moderated.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
This message was moderated.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
98 | |
11 | |
11 | |
6 | |
6 | |
4 | |
4 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.