Hi,

I uses BAPI_NETWORK_MAINTAIN function to schedule a network but when start date is older than today the function automatic user today for the start date. How can I use the start date older than today? Please help me!

Thank!

Edited by: Cuong Nguyen Cao on Feb 9, 2010 10:47 AM

Accepted Solutions (0)

Answers (3)

Answers (3)

Former Member
0 Kudos

Check your settings in tx OPU6, this is a configuration at plant level, enter to one of them, you will se a field called "Start in the past" press F1 on that one and there you will find your answer.

Also there is a checkbox for automatic scheduling, that might help you depending on your scenario.