on 02-09-2010 4:59 AM
RESPECTED ALL
IN MY SCENARIO WE HAVE ONE MATEIRAL CODE WHICH MOVE IN THREE DIFFERENT SHOP FLOORS
ACCORDING TO THE SHOP FLOOR WE HAVE CRETED THE TASK LIST. NOW THE PROBLEM IS WHEN USER DO MSC1
AND CONFIRM IT WITH CO15 WE GET INSPECTON LOT AUTOMATICALLY AND WE CAN SEE THAT INSPECTION LOT AT QA32 WITH THE SYSTEM STATUS CRTD AND WHEN WE CLICK ON THE USAGE DECISION SYTEM IS NOT ALLOWING US TO DO IT, THEN WE GO TO QA02,ASSIGN ONE TASK LIST TO THE LOT AND COME BACK AND GO TO QA32 AND NOW SYSTEM IS ALLOWING TO DO THE UD.
MY QUESTION IS, IS IT ANY WAY THROUGH WHICH WE CAN AUTOMATE THE UD PROCESS??
WE HAVE 3 DIFFERENT PRODUCTION ORDERS WHICH DIFFERENTIATE THREE LOCATIONS.
WE WANT FOLLOWING SCENARIO
MATERIAL 1--
TASK LIST 1
MATERIAL 1--
BATCH 2 -
TASK LIST 2
MATERIAL 1--
TASK LIST 3
THANKS
ABHAY
Hi,
As you have created 3 task lists for one material with same usage, system will not understand when to use which task.So you will have to go to QA02 and assign the task list manually whichever you want and then proceed.
Vishal
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Thank you vishal for the reply
is the only way??? why i want to avoid this manual assignment because if by mistake user from shop floor 1 assign the task list of shop floor 2 then our reports will shatter like anyting. so can we not assign it on the basis of production order?? as the production order is different for each shop
regards
abhay
User | Count |
---|---|
98 | |
11 | |
11 | |
6 | |
6 | |
4 | |
4 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.