Hi,

I am facing a problem while running of RA

1. Sales Order Created - Project Created in Back Ground

2. Incurred actual cost/revenue

3. Running RA for Project

When I run RA it is not showing the Sales Value as Planned Revenue,

but it is showing in the s_alr_87013531

Please help me.

Thanking you

Shareeq

Accepted Solutions (1)

Accepted Solutions (1)

virendra_pal
Active Contributor
0 Kudos

you need to configure RA transactions OKG1 to OKG5 and also check the line ID configuration where you can specify the value category for revenue

shareeq_hussain
Active Participant
0 Kudos

Dear Virendra,

RA configuration is complete. Only the revenue part is not appearing in KKA2.

Regards,

Shareeq

Answers (1)

Answers (1)

Former Member
0 Kudos

Hi,

In OKG3,under expert mode please check under planned values which Overall plan Method you are using,Is it E,F M.

Muzamil

shareeq_hussain
Active Participant
0 Kudos

Assalamu Alaikkum Muzammil,

Overall Plan is E. RA Type - E.

Planned Cost in CJ40 for WBS Element is 105.

Planned Revenue in WBS--Sales Order is 120.

But RA shows Planned Cost 105 and Planned Revenue 105 if Overall Plan is M in OKG3.

If I am correct , Planned Cost Should be 105 and Planned Revenue should be 120. Correct me if am wrong.

Thanks

Regards,

Shareeq

Edited by: K M AHAMED SHAREEQ HUSSAIN on Feb 9, 2010 12:06 PM

Edited by: K M AHAMED SHAREEQ HUSSAIN on Feb 9, 2010 12:06 PM

Former Member
0 Kudos

Hi,

Are you doing detailed cost planning or overall cost planning?

Try CJ42 for one project and run and check the results.

1.In my system i am using overall cost planning and revenue planning through Sales order billing plan and i am using Overall Plan is M and it is working fine.

2.In other company i am using detailed cost planning by cost element wise and manual revenue planning cost element wise ,here i use Overall Plan is F and i am not facing any issues.

Muzamil

shareeq_hussain
Active Participant
0 Kudos

Dear Muzamil,

We are doing Overall Cost Planning in CJ40.

My Understanding is Costs are planned in CJ40 and Revenue is Planned based on Sale Order Value.

May i know the difference between CJ40 and CJR2.

Regards,

Shareeq

Former Member
0 Kudos

Hi,

In CJ40,You can plan yearly/Cost element wise and overall on WBSE elements.

Muzamil

shareeq_hussain
Active Participant
0 Kudos

Thanks a Ton, Virendra and Muzammil.

The Line ID setting for Revenue was missing. My Problem is solved

Keep up your good work.

Regards,

Shareeq

Edited by: K M AHAMED SHAREEQ HUSSAIN on Feb 15, 2010 11:36 AM