Hi All,

Our requirement is that whenever a buyer changes text in ECC PO a change PO should be triggered in SUS.

As of now the changed PO is triggered only when date,qty,price is changed in the ECC PO.

Pls advise how to get this done.

Thanks,

Venky

Accepted Solutions (0)

Answers (1)

Answers (1)

samar_jose2
Contributor
0 Kudos

Hi, You can try BADI BBP_DOC_CHECK_BADI with method BBP_DOC_CHECK. Ask your abaper to make the necessary change to your requirement.

I hope this helps.