HI,
can u let me know that release of physical samples depends on which setting?
say, physical samples are created during Insp Lot creation, now we have two possibilities:
a) sample are in status REL..xxxxx.... - no need to do QPR4
b) samples are in status CRTD...xxxx....they are to be released via QPR4 , where do we define this.
Regards,
Rajat
In Sample Drawing Procedure QPV1/2/3, there is a checkbox, which determines the automatic/manual release of sample drawing. Its called " Confirmation Required for Physical Sample"
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
As per my knowledge when Phys sample is automatically created it is in release state.
When you create it manually it has be released.
This is defualt SAP.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.