on 02-05-2010 7:33 AM
Hi All,
We have some planned orders generated in APO and system automatically sends them back to ERP. Each of them has several "Activities". We need to transfer the activities to ERP so that ERP can calculate start time and end time in each work center.
However, the activiteis of planned orders are not transferred back to ECC. By debugging the FM CIF_ORDER_INBOUND_30A, we found that none of the parameters contain the actitities information.
Can anybody tell me how to enable the transfer of planned order actities information to ECC? Should we do it via configuraiton or development.
Thanks
Jerome
Jerome,
Standard SAP does not support your requirement if you're doing production planning in ECC.
If you're converting planned orders into Production orders in ECC, system will only populate basic dates, start and end dates.
If production planning is to take place in APO-PP/DS, you will convert the APO
planned orders from APO into production orders. The only thing that distinguishes
an APO production order from an APO planned order is its conversion indicator.
If the conversion indicator has been set in APO, a corresponding ECC production
order is created in ECC. The production dates that have been determined in APO
are transferred to this order. In addition, as with all ECC production orders,
it contains all the functions needed to execute production (printing of order
documents, confirmations, and so on).
If you're not using PP/DS, then you have to go for a custom development to realize your requirement.
regards
Mohan
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi Mohan,
Thanks a lot for the explanation.
In our scenario, only finished goods is planned in APO. The planned order is transferred back to ECC. They're converted to production orders in ECC.
Can you or anybody tell me what program I should enhance so that the start and end time of activities is sent to ECC?
Thanks
Jerome
Hi Jerome,
Try running /sapapo/ccr for the planned order between
ERP and APO system and check any activity errors are
captured.
Regards
R. Senthil Mareeswaran.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi,
As far as my knowledge APO doesnot transfer planned order activity information to ECC it only transferes basic dates and according to ECC setting production dates are filled. Still you can find out work center wise start and end dates for each operation In det.scheduling tab of planned order. Still you cannot find information activitywise.
Regards,
Santosh
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
7 | |
4 | |
3 | |
2 | |
2 | |
1 | |
1 | |
1 | |
1 | |
1 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.