on 02-04-2010 9:17 AM
Hi Friends,
There is a requirement that I have to create projects and activities automatically.
I need inputs that how can i proceed?
All the configuration are done and project profile is maintained.i am assuming that my initial customized t code's initial screen shud be look like project/wbs/network sub tab.
Now in project ub tab-- i will give proj defn, description,creation date,proj profile and proj start and finish date( all with range selection)
In WBS sub tab--WBS element with range selection, WBS Element description field with range selection WBS creation date with range selection and three check boxes for operative indicators (planning, account, billing).
In network sub tab-network no with range creation date with arnge network profile .
And i will use the tables PROJ/PRPS/AUFK
Is it the right way to srtart the design?
Any pointers.
Regards
Ashu
Suggest you you should use BAPI for this requirement.
BAPI_PROJECTDEF_CREATE Create Project Definition
BAPI_PROJECTDEF_UPDATE Change Project Definition
With Regards
Nitin P.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
closed
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi Ashutosh,
There is a facility of making Standard WBS, Standard Networks & Standard Milestones.
In creating customized screens for entering the Project Definition, WBS levels & networks you would in turn be copying the detilas from existing projects.
So might as well keep make use of standard structures which can be customized much more easily.
Regards,
Mangesh Kamat.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
95 | |
11 | |
11 | |
6 | |
6 | |
4 | |
3 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.