Hello,
I have a simple question , i think.
How to create activity relationships in a PPM?
I created PPM's for a few materials via integration model from R/3 and there was automatically an activity relationship created.
I want to add additional relationships but have no idea what to do?
Kind regards,
Bert
Hi,
There is symbol indicating double arrows go to change ppm and click on that symbol to maintain extra relationship.
santosh
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi Bert,
In the operation overview of the routing transaction, click on
control plus F6 so that it will take you through the graphical
display of the operation sequences
Then based on the sequence, you can amend the operations
accordingly
Regards
R. Senthil Mareeswaran.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi Bert,
Since you are CIFing the Production Version from ECC / R3, you need to change the relationships in Routing or Recipe. If you you check Operations for your recipe or routing, you will find the relation and you can specify your predecessor, successor & your relation type.
Hope this helps
Thanks
PavaN Sarda
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
10 | |
3 | |
2 | |
1 | |
1 | |
1 | |
1 | |
1 | |
1 | |
1 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.