I have a simple question , i think.

How to create activity relationships in a PPM?

I created PPM's for a few materials via integration model from R/3 and there was automatically an activity relationship created.

I want to add additional relationships but have no idea what to do?

Kind regards,

Bert

Accepted Solutions (1)

Accepted Solutions (1)

Former Member
0 Kudos

Hi,

There is symbol indicating double arrows go to change ppm and click on that symbol to maintain extra relationship.

santosh

Answers (2)

Answers (2)

Former Member
0 Kudos

Hi Bert,

In the operation overview of the routing transaction, click on

control plus F6 so that it will take you through the graphical

display of the operation sequences

Then based on the sequence, you can amend the operations

accordingly

Regards

R. Senthil Mareeswaran.

Former Member
0 Kudos

Thanks,

Apparently, we create these relationships in a use exit.

Anyway,

Thanks for the help.

0 Kudos

Hi Bert,

Since you are CIFing the Production Version from ECC / R3, you need to change the relationships in Routing or Recipe. If you you check Operations for your recipe or routing, you will find the relation and you can specify your predecessor, successor & your relation type.

Hope this helps

Thanks

PavaN Sarda

Former Member
0 Kudos

Yes,

This seems very logical to me and that was where i was looking too, but i think i need glasses because i don't find it in my routing.

Can you help me to find it?

Kind regards,

Bert