Hi all,
All cost planning i have done in object currency(INR),but in s_alr_87013533 report it shows the values in controlling area currency.How can the values be seen in object currency in the reports?
hi
go to cje2 and select perticular report ,dabel click on the lay out ,then lay out appears in righat hand side>go to change mode dibel click on 'key figers" change the currency figer from controling currency to object currency then save & execute the report.
thank you
regards
bhavani rao
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Martina,
use this way to translate to object currency,if project is cross several month and ex.rate define
are different,how to get the real object currency amount for by each period? it may have little difference
from ths traslation...
Regina
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Chirald,
Once the report is executed, please call Settings > currency. You will be able to select the desired currency there.
Hope this helps
Rgds
Martina
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Just change the layout setting.
Go to Settings >> Layout >> Change and choose "Value in Object Currency"
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.