Hi All

I am doing assembly processing for project with varient configeration

When I create and save sales order for a material taking quantity as 1 a project is being generated for SO with quantity 1 for a material

when I put quantity more than one in SO say 2 , the project is bening generated with quantity for material as 1 ony.

My requirment is the project should get generated with quantity 2 ( equal to SO quantity)

any setting required for transferring quantity of material in SO to project ?

waiting for reply

shashank

Accepted Solutions (1)

Accepted Solutions (1)

former_member203108
Active Contributor
0 Kudos

System uses execution factor for sales order quantity. Enter execution factor in standard network as '1' ie., the network, activities and materials are assigned for 1 no. of sales order quantity. if your sales order quantity changes to 2, then system will change the execution factor to 2 and so the material quantities in network.

Try this.

Answers (0)