on 02-04-2010 5:44 AM
Dear Sir
In our scenario we required unless quality inspection plan is not created Purchase requisition (manual/system) should not be generated.
It can be PO too
Regards
kunal
No link with QM can resolve this. This is really a material master creation process.
This requirement could probably be handled by using material statuses and workflow. I'd ask about this in the MM forum or Workflow.
Craig
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Dear Kunal
Please tell me in what business scenario you want this requirement. The best would be activate quality info record requirement for all material
So when Purchase wants to procure a new material , quality info record has to be created and so quality personnel will come to know that the new material is going to get procured.
I dont think you should take this requirement.
Regards
Gajesh
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Dear Sir
Its of our Project Div.
every time lot come to crtd and during month end project material are too many and so many plants.So it has been decided to create plan first than the PR should be generated if no plan no procurement to be done.Sir we hade z report which shows which has no plan but acceptable they want system locking.
So please guide
Regards
kunal
Hi Kunal,
I dont think there is any standard way to do this.But what Ganesh suggested looks helpful to me.
First check with your ABAP developer that there is any user exit available at the save of quality info record which can look that inspection plan for the material & plant combination has been created or not.If it is available then activate quality info record for all materials and get the logic developed for checking before saving ,if not dont allow user to create QI record.
So once Quality person wants to create the inforecord he has to make sure that inspection plan should exsits in the system otherwise no inforecord & in other way no PO.I think in this way we can achieve the compliance(its just a thought i never did this).
Cheers,
Tushar
hi,
I do not think so , there is a link b/w Q plan and the PR creation.
anyway wait for the experts ans.,
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
97 | |
9 | |
8 | |
6 | |
3 | |
3 | |
3 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.