Availability control on Budget Control System (BCS)

Former Member
0 Kudos

Hi,

Availability control on Budget Control System (BCS) is always carried on an annual basis amount; despite that initially the budget is registered per month (for statistical facts).

Is it possible to control availability per period or per month?*

Thank you

Adriana

1 ACCEPTED SOLUTION

iklovski
Active Contributor
0 Kudos

Hi,

It's possible within the release EPH4 with the object 'budget period'. For earlier releases, there is workaround of creating 12 different ledgers in AVC and manage them by month, but it's very tricky.

Regards,

Eli

View solution in original post

2 REPLIES 2

iklovski
Active Contributor
0 Kudos

Hi,

It's possible within the release EPH4 with the object 'budget period'. For earlier releases, there is workaround of creating 12 different ledgers in AVC and manage them by month, but it's very tricky.

Regards,

Eli

Former Member
0 Kudos

Hi,

Thanks for your information.

Bye