02-03-2010 10:58 PM
Hi,
Availability control on Budget Control System (BCS) is always carried on an annual basis amount; despite that initially the budget is registered per month (for statistical facts).
Is it possible to control availability per period or per month?*
Thank you
Adriana
02-04-2010 8:56 AM
Hi,
It's possible within the release EPH4 with the object 'budget period'. For earlier releases, there is workaround of creating 12 different ledgers in AVC and manage them by month, but it's very tricky.
Regards,
Eli
02-04-2010 8:56 AM
Hi,
It's possible within the release EPH4 with the object 'budget period'. For earlier releases, there is workaround of creating 12 different ledgers in AVC and manage them by month, but it's very tricky.
Regards,
Eli
02-04-2010 7:20 PM