on 02-03-2010 10:43 PM
How we can explode the order in PPDS (by using the Switch Source of Supply function)
Please let me know
Thanks
Sunil
Hi Sunil,
The explosion of PPDS orders will be executed based on the
product master under PPDS tab in Order creation. If no
value is specified, system uses the value from customisation
Regards
R. Senthil Mareeswaran.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi,
Go to product veiw-/SAPAPO/RRP3.
double click on order click on change button. Then change source of supply this will explode the order again.
Check that order is not PP firmed or output firmed.
Hope this helps.
Regards,
Santosh
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
7 | |
4 | |
3 | |
2 | |
2 | |
1 | |
1 | |
1 | |
1 | |
1 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.