on 02-03-2010 10:00 PM
Hi All,
I have a situation with Confirnation dates.
In our business, we ship goods out only on a friday. So, assume we have a sales order and after the ATP check, the schedule line confirmation is on say wednesday. We want that to be friday instead of wednesday. If the confirmation date is a friday, we would leave it as it is.
Any ideas how we could do this? I created a new factory calender with only fridays as workdays and assigned it to the shipping point thinking that it would do some thing. It had no effect at all. Then I tried created a new route and assigned the same factory calender to it. It too had no effect as the route days is set as 0 days. I tried assigning one day in the route but it shows teh friday of next week.
Any ideas would be appreciated.
Thanks & Regards,
Vidya Sagar
closed
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
100 | |
11 | |
11 | |
6 | |
6 | |
5 | |
4 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.