Factory Calendar not working for holidays.

Former Member
0 Kudos

Hi Experts,

In my factory holiday calendar 1st-5th of X month are set as holiday. I have assigned this calendar to my plant.

When I process a sales order with delivery date 2nd of X month, System is creating the sales order without stop.

How is it possible ? Is factory calendar settings not working ?

Please suggest me the possible root causes and fixes for this.

The sales organisation in which I am creating sales order does not have any calendar. Does it have any bear on the issue?

Appreciate any quick response.

Accepted Solutions (0)

Answers (2)

Answers (2)

Former Member
0 Kudos

Hi,

Maintain Calendar for the sales organization to get impact in sales order

Goto OVX5 , choose your sales organization,

click on details,

Detailed information tab - Sales Org Calendar (maintain your factory calendar)

Regards

Senya

Former Member
0 Kudos

Hi Senya,

Thank you for the response.

Me also want to test " Assigning the calendar to the sales org" but I have 2 questions.

  1. If, I assign the the holiday calendar to sales org along with plan, and create a sales order in those holidays, what happens ?

  1. If I do, Holiday calendar assignment only to the plant not to the sales org , What happens ?? In which of these two cases, system stops from creating delivery ?

Please be detailed to explain how system responds in the above two scenarios.

Your inputs will help me to decide on the next course of action.

former_member187989
Active Contributor
0 Kudos

It should have impact on billing documents,have u checked it ?

If u assigned factory calender to plant,Check whether u assigned respective factory id to invoicing dates of billing documents tab in sales area tab of customer master.