i work in a company that sells lifts.(we also produce them). Every lift is different and depends on the value of different characteristics. So I have thougth that the most convenient option would be to create a configurable material so that it would be possible to create a sales order and configure this material in the sales order. Then it would be produced and finally it would be delivered. The problem is that our lifts are not delivered in one part. First we deliver the mechanical part and then the electrical part.

I don't know if this is possible.

Thanks in advance.

Luis.

Accepted Solutions (1)

Accepted Solutions (1)

Former Member
0 Kudos

HI,

Maintai Item category group LUMF in material master

Determine Item category TAP for main item and TAC for subitems in sales order

In VOV7 >>> Item category detail >>> Tick mark to schedule line allowed

Then u can able to deliver it seprately