We are making PR through CJ20N with account assignement as WBS.
I have one PR whose partial quantity PO has been made, now i dont want further quantity so i want to block this PR so that i will not show as PR committment. How can i do this?
Regards,
Kalpesh
Hi,
1.Change the Requirement qty as equal to PO qty in Project builder under the Purchasing date of the Material.So in this case the PR commitment will be reduced and only PO Commitment will show.
2.If you Dont want to change the requirement qty same as PO qty,then TECO the activity where the material is attached,in this case PR commitment will not show.
Muzamil
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Kalpesh,
as far as I know the logic is not the same depending if reduction is value based or quantity based...
You can always mark the PR item as deleted, but I guess you should post this thread in the MM forums where the experts in the area will be able to provide a more accurate answer.
Regards
Martina
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
107 | |
12 | |
11 | |
6 | |
5 | |
4 | |
4 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.