02-03-2010 12:38 AM
Hello Guy's . We would like to run more one payment run FPY1 simultaneously for different programs. However the system locks the relevant BP or CA during this process, hence we cannot run more than one payment run at a time. This causes a lot of delay as we have to wait for each payment run to finish. Is there a way where we can run more than one FYP1 or FPMA at a time. Will fpscheduler cater this. I think there should be a way where you can do it as PSCD is designed to process huge volume of data for different activities. Please advise.
Thanks in advance
Saj
02-04-2010 11:48 PM
Read up on the technical settings tab in the payment run. This enables you to create smaller intervals that the mass jobs need to lock. Are you using the Parallel Processing Object?
02-15-2010 4:10 AM
Hi, Currently we are using BPART which locks all the other CA whilst payrun we are trying to use VKONT and increase the jog interval. SO that simultaneously several payment run can be executed.
Saj