Activity confirmations

Former Member
0 Kudos

I'm having trouble cancelling the CNF system status on activities.

I'm fairly certain that the process should just be CN29 to cancel the confirmation, whereupon I ought to be able to transfer (posted time) to PS using CAT5.

However, the transfer errors because the activity remains finally confirmed, even though the system status is partially confirmed and the user status is "open". It's almnost as though the CNF status is still in the background somewhere.

Does cancelling the last confirmation (in CN29) and removing the "F" marker, reset the status for the entire activity, or do previous confirmation numbers marked with "F" somehow continue to operate in the background, and thereby preventing transfer to PS in CAT5?

I've tried making corrections in CN25, unticking the "completed" box and making the % complete less than 100%, but still get the same error message when I run CAT5.

Any help gratefully received!

Accepted Solutions (0)

Answers (1)

Answers (1)

Former Member
0 Kudos

cancel the same through CAT5 instead of confirmation cn25

Rgds

Prem