on 01-31-2010 10:33 PM
Gurus,
I am working with both 03 & 04.I am also working with 04 onlyfor some materials.For 04, though i have given 1 in task list it is still
picking 5 for somewhere though i have not created any Qplan with 5 in QA32.When i assign the 1 i am able record results &
usage.Where is the problem.What should i use in Qplan for 04 1or 5?
Hi,
As Sujit Ji said, the inspection type picking the Qplan usage which is you assigned in the img screen for that type.
Check Qcc3>Inspection lot creation->maintain Inspection type>04 inspection type->check usage in 04
If you assign the usage 5 in the inspection type 04 and if the usage 5 is maintained in the Qplan .
so system automatically pick the uage 5 for this inspection type 04
so if u need usage 01 for the inspection type 04.
go to the path.,
Check Qcc3>Inspection lot creation->maintain Inspection type>04 inspection type->check usage in 04
Enter uage as 01.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi
Where is the problem.What should i use in Qplan for 04 1or 5?
No doubt Usage must be 1.
Check Qcc3>Inspection lot creation->maintain Inspection type>04 inspection type->check usage in 04 inspection type.
here it must be 1
Regards
Sujit
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
94 | |
11 | |
11 | |
6 | |
6 | |
4 | |
3 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.