on 01-31-2010 6:26 AM
Dear Experts,
My Requirement is to create Project in the Background with Sales Order No instead it is creating with Inquiry No.
The same thing is working in another Server. Am not able to locate the problem.
Please help me.
Regards,
Shareeq
Answered. Thanks Guys for all the info
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
The requirement of yours can be achieved through assembly processing.
Below are the some of config which needs to be done.
1. In Material Master-->MRP 3 view select the strategy for that material as 83: Assembly processing with networks OR 85: Assembly processing with network/project.
2. In the transaction code CN08 do the assignment for Standard network and sales order type and if you want also to create the WBS elment then assign the std network to the std WBS element.
3.Tthe coding mask of the project should match the sales order number ranges.
Cheers
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Check S.O. Item category or Document type.Reuirement type is get derived from either SD ITem category or Materila Master Staregty group. As in your case material is same .
This is happening due to Docuemnt type, your doument type should refer to correct SD Item categoty from that combination you will arrive to requirement Class.
Please check below customization.
Project System>Material>Control of Sales-Order-Related Production-->Check Control of Requirements Type Determination
Project System>Material>Control of Sales-Order-Related Production-->Selection of Requirements Type Through SD Item Category
Check out this thing you will get clear cut picture.
WIth Regards
Nitin P.