hi all,

I want to schedule material specification for manual inspection lot. how i can do this? so that when i create manual inspection lot only material specification scheduled for that date and time should come in inspection lot.

thanks all

Accepted Solutions (0)

Answers (1)

Answers (1)

former_member42743
Active Contributor
0 Kudos

Manual inspectons using material specs will use the material spec in place at the time of the creation of the inspection lot.

My only suggestion is when creating the lot via QA01 change the start and end date to a future date and see if it picks up the correct spec.