Hi,

In our BI system, we want to avoid that dialog workprocess entering in private mode.

Now we have the next situations:

Number of dialog workprocess: 30

rdisp/wppriv_max_no: 25

rdisp/max_priv_time: 600

We had thought to change this parameters to:

rdisp/wppriv_max_no: 15

rdisp/max_priv_time: 3600

Do you think these new parameters are correct or that we can to have some problems whit them?.

Best Regards

Accepted Solutions (1)

Accepted Solutions (1)

Former Member
0 Kudos

I wouldn't increase rdisp/max_priv_time; read SAP note 79435.

In your old setting up to 25 processes are allowed to stay 10 minutes in priv mode.

In your new setting up to 15 processes are allowed to stay 1 hour in priv mode.

You can't really compare these two scenarios, but I don't think the second one is better.

regards

Former Member
0 Kudos

Thanks Joe for your answers,

The problem is that our functionals want the dialog process can work at least 1 hour in private mode.

Do you think is better the last situation with the parameter rdisp/max_priv_time in 10 minutes?.

Regards

Answers (2)

Answers (2)

Former Member
0 Kudos

I would suggest you to check/tune your memory parameters to start with. Please check attached link for more details.

[http://help.sap.com/saphelp_nw04/helpdata/en/02/96253c538111d1891b0000e8322f96/frameset.htm]

Former Member
0 Kudos

Hi,

    • Do not copy and paste*

Read the "Rules of Engagament"

Regards,

Ravi

Edited by: Juan Reyes on Jan 29, 2010 12:01 PM

Former Member
0 Kudos

Thanks Ravi, more or less I understard this, but I'm not sure if these values for this parameters are correct.

What do you think?.

Regards.

Former Member
0 Kudos

Hello Maximino,

as so often: It depends.

And as I wrote: You can't really compare these two scenarios.

The new setting could result in this:

20 work processes in priv mode since about 45 minutes.

20 other work processes in priv mode since about 30 minutes.

All the other work processes in priv mode since about 15 minutes.

So nobody else will be allowed to work. This will only change in 15 minutes, when those exceeding 60 minutes will be cancelled.

On the other hand, if know know for sure that only a few of your users will go priv, your suggestion will work.

There are a lot of SAP notes or help texts about priv mode. You might want to look for different solutions. Or it might be necessary to buy more memory for your SAP server.

regards