cancel
Showing results for 
Search instead for 
Did you mean: 

Planned Cost linked to Quatation Creation in SD

Former Member
0 Kudos

Hi Everybody,

As per the requirement, when i release the WBS, basing on the planned values Enquiry/Quatation has to be generated in SD.

Pl. guide for the same.

Regards,

Accepted Solutions (1)

Accepted Solutions (1)

Former Member
0 Kudos

According to the WBS defined in the project type, please check for all the parameters in the customization part of project type, which will be defined for the WBS element.

Hope this will be of a little help.

Regards,

Vittal

Answers (2)

Answers (2)

Former Member
0 Kudos

since the requirements are changed we are closing the issue.

virendra_pal
Active Contributor
0 Kudos

please read SAP help

there is no standard solution for this

you will need to configure the set up then have a program or exit to trigger the creation of quotation using sales pricing functionality on releasing WBS