POC Iis not showing 100%.

Former Member
0 Kudos

Hi Gurus,

Need help here..

The status CLSD cannot be set on the project because POC is not 100%! --> allthough the relevant progressive act. costs are higher than the prog. plan costs.

What to do?

thanks

Tanuj

Accepted Solutions (0)

Answers (2)

Answers (2)

Former Member
0 Kudos

Tanuj,

First of all, review your customizing under

Project System > Progress >Progress Analysis > Define Measurement Methods. For the method used, check the value in field Max POC and also the F1 help for this field.

The system determines the percentage of completion (POC) for a period from the ratio of planned or actual costs to the cumulative planned costs. The system determines the planned or actual POC as follows:

Planned POC = Planned costs/cumulative planned costs * 100

Actual POC = Actual costs/cumulative planned costs * 100

The planned costs are considered up to the time of the calculation.

The cumulative planned costs are the planned costs over the whole duration. You use the progress version to stipulate which cost plan the system uses (annual=years dependant or overall=years independent).

Hope this helps

Best regards

Martina

Former Member
0 Kudos

Tanuj,

What progress method are you using?

Thanks

Martina

Former Member
0 Kudos

Hi Martina,

Thanks a bunch for looking into this.We are using Cost Based POC method under Result Analysis.

BR,

Tanuj

Former Member
0 Kudos

Apologies its revenue based Profit analysis