Dear All,
The client received (GR) 100 PC through PO from vendor in project stock (say each PC value 50 INR), now if i have done all 100 PC good issue (221 Q) to project out of which 70 I consume to project & 30 PC get damage ( its value get decreases say each PC value 30 INR) now i want to return this 30 PC to plant stock not in scrap or block stock at lower valuation how i can achieve this process ?
Regards
First make consumption reversal for 30 Units from the project with 222 Q in transaction MB1A. Second step will involve change the price of these reversed goods to the new value of INR 30 in transaction MR21(choose project stock here for re-valuation). Third step will involve transferring these materials to plant stock with movement 411 Q. in transaction MB1B.
Regards,
Mahendra
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
110 | |
12 | |
11 | |
6 | |
5 | |
4 | |
4 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.